Open Obosi end of Bridge Head to ease suffering of commuters in Anambra NUF cries out

 Obosi Bridge Gridlock : Open Closed Obosi Bye Pass now, 

NUF Tells Julius Berger


The Ndigbo Unity Forum (NUF), has called on the Julius Berger Construction Company handling the Second Niger Bridge to open up Obosi end of the bridge to reduce the suffering of users of Onitsha-Owerri road.


The group in a statement  this  weekend Onitsha said the company closed the Obosi Bridge bye pass  end and diverted the traffic to one side for almost two months which has caused traffic grid lock on the road and untold hardship to the people. 


In the statement signed by Dede Uzor A Uzor, the group Grand Patron said the company has failed to  live up to the their contractual agreement in the handling of the second Niger Bridge.


NUF said the bye pass was closed apparently to allow them carry out their construction work but unfortunately, for the past two months,no work was being done on that road.


They said Julius Berger first gave December 2021 as the completion date of the bridge, then shifted it to  February 2022 .


At other time, said NUF, they shifted the completion date  to April 2022, now they have moved the goal post to October 2022.


Describing the continuous adjustment of completion date  as  a sign of unseriousness on the part the company  , NUf asked Federal Government to put pressure on Julius Berger  to complete the project once and for all on or before October this year for  the overall interest of the generality of the people of NIgeria.


The group also asked the  Federal Government to ensure that the company is funded as and when due to avoid some hitches on their part so as to meet the latest deadline. Grand Patron Dede Uzor cautioned. 

30th April 2022